So you bought some kitchen cabinets…  There not much good without installing them.  Here is generally how the process works when the Kitchen Gallery gets involved with the installation of cabinetry and counter tops.  In advance of cabinet arrival, we will put together an installation proposal for customer to review.  The first day of installation will often be a Monday so we have the benefit of a full work week.  That installation schedule could look something like this:

APRIL 1 (MONDAY) — remove and dispose of existing cabinetry — KITCHEN GALLERY

APRIL 1 (MONDAY/TUESDAY) — remove and dispose of existing tile flooring — KITCHEN GALLERY

APRIL 1 (MONDAY/TUESDAY) – electrical rough ins, if any – KITCHEN GALLERY

APRIL 2 (TUESDAY) – continue to remove flooring as needed start new floor install – KITCHEN GALLERY/FLOORING COMPANY

APRIL 3 (WEDNESDAY) – continue tile floor install – FLOORING COMPANY

APRIL 4 (THURSDAY) – continue tile floor install – FLOORING COMPANY

APRIL 5 (FRIDAY) – complete tile floor install – FLOORING COMPANY

APRIL 5 (FRIDAY) – start cabinet installation if flooring is completed – KITCHEN GALLERY

APRIL 8 (MONDAY) – start/continue cabinet installation – KITCHEN GALLERY

APRIL 9 (TUESDAY) – continue cabinet installation – KITCHEN GALLERY

APRIL 9 (TUESDAY) – arrange for appliance delivery — HOME OWNER

APRIL 10 (WEDNESDAY) – complete cabinet installation – KITCHEN GALLERY

APRIL 10 or 11 – template countertops for granite – KITCHEN GALLERY

APRIL 18 (WEDNESDAY) – install granite countertops — KITCHEN GALLERY

APRIL 19 (THURSDAY) — plumb up kitchen sink and dishwasher — KITCHEN GALLERY

The process lasts about 2-1/2 to 3 weeks when a templated countertop is required (i.e. granite, quartz or Corian).  Although the project is often 100% complete in that 2 to 3 week time period, the main goal the Kitchen Gallery has is to get your kitchen sink running.

If I can be more specific, please post a comment below.

 

 

 

The post Installation Process appeared first on Kitchen Gallery -- cabinets, countertops, design and installation.



from http://nhkitchens.com/installation-process/

No comments:

Post a Comment